SMALL CYLINDERS INSTALLATION INSTRUCTIONS

All the installation operations should be executed with care in order to avoid any permanent deformation of the material. To avoid contamination, keep the material in the casing until installation. The installation area must be kept clean.

Clean (wash) the tank before installing the Explosafe® Cylinders

Pour the Explosafe® Cylinders into the tank/container.

Pay particularly attention on filling the entire tank’s volume. In case, shake the tank/container several times during the filling so that the material is displaced properly.

Once filled the entire volume, shake the tank/container once more and pour some more material into the tank. If required, apply a small pressure. Some 5-10% overfilling is recommendable.

Once the installation has been completed and before using the tank, it is preferable to carry out three cycles of filling and emptying of the tank with the same fuel that will be subsequently used (gasoline, kerosene, JP4, etc…), in order to eliminate any possible contamination.

After each emptying and during the phase of preliminary washing, it is recommended that any residue be aspirated from the exhaust orifice.

The fuel utilized to wash the tank can be re-used, after being filtered.


IMPORTANT NOTES:
If veicle uses an in tank fuel pump, then make sure that the electric connections are insulated before instalation of Explosafe
®.
Otherwise there is a risk of shortcircuit. To avoid any problem, please do not leave any “not isolated” electrical wire in contact with Explosafe®
Make sure that any pumps is placed after the filters (in the motorbikes, the extreme working conditions might cause some flaking. If the filters are placed properly there is no problem).